Haryana RERA QPR 2026: Due Dates, Form QPR-1 and Penalties

Last updated: 14 October 2026

The Haryana RERA QPR (quarterly progress report) is due within 15 days of the end of every quarter: by 15 April, 15 July, 15 October and 15 January. Every promoter of a registered project in Haryana must upload it under Section 11(1) of the RERA Act and Rule 14(1)(d) of the Haryana RERA Rules, 2017. The QPR for the quarter ending 30 September 2026 was due by 15 October 2026. The next one, for the quarter ending 31 December 2026, is due by 15 January 2027.

This guide explains what goes into Form QPR-1, the three professional certificates you need, and what HRERA Gurugram has done to promoters who did not file.

Building under construction with scaffolding, the progress a haryana rera qpr reports

Haryana RERA QPR due dates

Quarter endsQPR due by
31 March15 April
30 June15 July
30 September15 October
31 December15 January

HRERA Gurugram’s Quarterly Progress Report Regulations, 2018 (No. 12/RERA GGM Regulations 2018, dated 5 December 2018) say the same thing in plain words: the report “shall reach before 15th of subsequent month after end of quarter”. The regulations apply to every registered project in Gurugram district. Projects in the rest of Haryana file with HRERA Panchkula on the same 15-day rule from the Rules.

What the Rules require you to update

Rule 14(1)(d) lists the updates a promoter must upload on the project’s webpage within 15 days of each quarter:

What Form QPR-1 asks for

The Gurugram regulations add a detailed format, Form QPR-1, on the promoter’s letterhead. It is longer than most promoters expect:

SectionWhat you report
1. ParticularsProject, phase, licensed area, registration validity, quarter
2. Financial progressEstimated cost, projected vs actual spend, split into land, construction, infrastructure and EDC/IDC
3. StatusPercentage completion and likely completion date for every tower, block or shop type, plus each infrastructure item
4. Project accountOpening balance, receipts, spend and closing balance of the separate RERA account
5. Government duesEDC and IDC payable, paid and backlog
6. CertificatesArchitect, engineer and chartered accountant certificates
7. ApprovalsApprovals received during the quarter
8. MiscellaneousChannel partners with HARERA numbers, legal cases, sale report, latest marketing material and latest advertisement details

The financial section asks a direct question: is the project on schedule as per actual expenditure? If not, you have to give the reason and how you will cover the backlog.

Site engineers in reflective vests checking construction progress

The three certificates

Each Haryana RERA QPR in Gurugram’s format is backed by three professionals:

  1. Architect’s certificate (Annexure 6-A): percentage of construction work done for each tower and each common facility, signed by an architect with Council of Architects registration.
  2. Engineer’s certificate (Annexure 6-B): cumulative cost incurred on construction and on internal and external development works.
  3. Chartered accountant’s certificate (Annexure 6-C): money withdrawn from the separate RERA account, and confirmation that withdrawals went only to land, construction and statutory dues.

Book these professionals for the first week after each quarter ends. The 15-day window is short once site photos, certificates and the sale report all have to line up.

The marketing part most promoters miss

Section 8 of Form QPR-1 asks for three things that sit with your sales and marketing team, not your site team:

In other words, HRERA sees your ads every quarter. Every ad must show the project’s RERA registration number and the Authority’s website, and must not promise anything the sanctioned plans do not support. Our guide to RERA advertising rules covers what to check before an ad goes live, and channel partner commission in real estate covers how partner deals are usually structured.

Want ads that you are happy to attach to your QPR? Message us on WhatsApp. We run RERA-compliant Google and Meta campaigns for builders in Haryana and Punjab, and keep a clean record of every ad that ran.

Message us on WhatsApp

What happens if you do not file

The RERA Act gives HRERA wide powers. Section 61 allows a penalty of up to five percent of the estimated cost of the project for contravening the Act, and Section 63 covers failure to comply with the Authority’s orders. HRERA Gurugram has used these powers on missing quarterly updates:

There is also a softer cost. HRERA’s public list of registered projects shows a QPR status column, and projects that have not filed show “QPR not Uploaded”. Buyers and channel partners can see that before they ever call you.

Haryana vs Punjab QPR

HaryanaPunjab
Due15 days after quarter end15 days after quarter end
Late feePenalties under Sections 61 and 63, case by caseRs 500 a day, up to 30 days, from 1 October 2026
Yearly filingAnnual audit reportForm-5 annual report by a CA

Punjab now has a fixed daily late fee. Our Punjab RERA QPR guide has the details for projects across the border.

Promoter reviewing a quarterly progress report before filing

FAQ: Haryana RERA QPR

When is the Haryana RERA QPR due?
Within 15 days of the end of each quarter, so by 15 April, 15 July, 15 October and 15 January, under Rule 14(1)(d) of the Haryana RERA Rules, 2017.

What is Form QPR-1 in Haryana RERA?
It is the quarterly progress report format in HRERA Gurugram’s 2018 regulations. It covers project particulars, financial and physical progress, the RERA account, EDC and IDC dues, professional certificates, approvals, channel partners, sales and the latest ads.

Which certificates are needed for the Haryana RERA QPR?
An architect’s certificate on construction progress, an engineer’s certificate on cost incurred, and a chartered accountant’s certificate on withdrawals from the separate RERA account.

What is the penalty for not filing the Haryana RERA QPR?
HRERA can impose penalties under the RERA Act of up to five percent of the estimated project cost. In one 2020 case HRERA Gurugram imposed Rs 25,000 per day for continued non-compliance and issued a show-cause notice for revocation.

Do channel partners appear in the Haryana RERA QPR?
Yes. Form QPR-1 asks promoters to list channel partners with each partner’s HARERA registration number.

The short version

The Haryana RERA QPR is due 15 days after every quarter, filed in Form QPR-1 with architect, engineer and CA certificates. It also asks for your channel partners’ HARERA numbers and your latest ads, so sales and marketing need to be ready too. Missing it can mean daily penalties, frozen accounts and a public “QPR not Uploaded” label next to your project.


Sources: HRERA Gurugram Quarterly Progress Report Regulations, 2018; Haryana RERA Rules, 2017, Rule 14(1)(d); HRERA Gurugram proceedings of 15 January 2020; Hindustan Times, 25 February 2024. Checked on 14 October 2026. This is general information, not legal advice.

Thank you for reading 🙏

A quick note on who wrote this guide: Leadproio is a digital marketing agency for real estate businesses in Punjab and Haryana. We’re not a property dealer or legal consultant, so we’re not able to advise on individual properties or paperwork.

What we do for builders, colonisers, dealers and brokers:

  • Google ads and Facebook and Instagram ads that bring enquiries straight to your WhatsApp
  • Google ranking for your website and projects
  • Google Business Profile setup and management
  • Websites and landing pages built to get enquiries

If you run a real estate business and would like more enquiries, we’d be glad to hear from you.

Message us on WhatsApp

Vaibhav Soni

Written by

Vaibhav Soni

Founder · Leadproio

Vaibhav Soni is the founder of Leadproio. He works directly with Punjab’s real estate builders, brokers and dealers on SEO, content and lead-generation systems built specifically for the Tricity belt.

More about Vaibhav

Leave a Reply

Your email address will not be published. Required fields are marked *